In brief

New US controls on advanced AI chips could have significant consequences for Southeast Asia’s fast-growing digital infrastructure sector. Effective 19 November 2026, a new interim final rule introduces destination- and end use-based licensing requirements affecting advanced computing items and remote access to computing capacity, with Singapore, Malaysia, Indonesia and Thailand among the markets potentially affected. For sponsors, borrowers and financiers, licensing requirements could delay equipment and operations, disrupt project timetables and revenues, strand costs and reduce GPU collateral value. Project participants should act promptly to identify affected facilities, customers and supply chains, clarify licensing responsibilities, strengthen KYC and export-control diligence, and review project and financing documents to address these risks.

The rule in brief

The US Department of Commerce's Bureau of Industry and Security (BIS) has published an interim final rule, "Addressing Remote Access to Advanced Semiconductors" (the IFR), which took effect immediately on 19 November 2026. Comments are due 60 days after publication. At a high level, the IFR: 

  • Imposes a new worldwide volume-based end use-based licence requirement for advanced computing items when there is “knowledge” that the items are destined for non-US data centres that provide remote access of more than 12,000,000 "aggregate TPP" of computing power to or for end users headquartered in, or whose ultimate parent company is headquartered in, China, Macau or another Country Group D:5 country (Restricted Companies).
  • Requires data centres already serving Restricted Companies at that scale to obtain a licence within 90 days.
  • Expects chip and server suppliers to obtain the data centre's know-your-customer (KYC) information and treats a refusal or inability to provide it as a red flag that presumptively gives the supplier "knowledge".
  • Clarifies that licences are required for data centres anywhere where a Restricted Company is otherwise the direct or indirect purchaser or “the exclusive or primary (greater than 50 percent of total compute) remote end user of the data centre computing capacity" regardless of aggregate TPP volumes.
  • Imposes a new destination-based licence requirement on all exports, reexports or in-country transfers of advanced computing items (regardless of end use or end user) to Indonesia, Malaysia, Singapore, Thailand and Brazil, with an exclusion for US-headquartered end users subject to monthly reporting.
  • Formally rescinds the Biden-era AI Diffusion Rule.

Southeast Asia is in the front line given four of the five countries BIS has named as diversion risks, namely Singapore, Malaysia, Indonesia and Thailand, are the region's principal data centre growth markets.

For greater detail of the changes implemented by the IFR, please refer to our blog on the IFR.

Considerations for sponsors and financiers of digital infrastructure and AI compute in Southeast Asia

1. Licensing

Given the recent developments, it is crucial for sponsors and borrowers to consider which entities in the structure have responsibility to obtain licences, ensure that licences are obtained, and plan for what happens to the project while licence applications are pending or if licences are not issued in a timely manner – particularly for pre-existing projects. For each transaction, a deal-specific matrix covering equipment, exporters, owners, operators, customers, ultimate beneficiaries and linked facilities should be prepared. Points to consider include:

  • For new deployments: The destination-based licensing obligation primarily sits with the exporter/ reexporter/ transferor of the chips, typically the OEM, server integrator or distributor, whereas the end use-based licensing obligation more likely sits with the operator or owner of the compute. In either case, all parties and their roles may need to be identified in licence applications. The project's delivery schedule depends on licence applications being made in a timely manner and on review times and outcomes nobody can yet predict. Licence timing should be built into construction milestones, commercial operation dates, delay liquidated damages and customer service commencement dates.
  • For existing deployments: The licensing obligation is generally with the operator, both for the retroactive licences for remote access to existing compute and for future changes in end use.
  • For US-headquartered customers: Projects anchored by US-headquartered hyperscalers can use the carve-out from the destination-based licensing requirement for exports, reexports or in-country transfers to Indonesia, Malaysia, Singapore, Thailand or Brazil, with monthly reporting by the exporter. Projects with regional or China-linked anchor customers have a materially different licensing profile.
  • Colocation and financing: Where required licences are not obtained, colocation providers whose tenants own, and lenders who finance the acquisition of, the advanced computing items may themselves potentially face liability for having stored, financed, or otherwise engaged with the advanced computing items with knowledge that a violation has or will occur (i.e., failure to obtain the required licences). A powered-shell or colocation sponsor and lenders may therefore still be drawn into the licensing analysis and into supplier and customer/end user diligence.

 

2. Terms of commercial contracts

Most existing data centre contracts were drafted on the basis that providing computing capacity as a service sat outside US export controls. That assumption no longer holds. Points which should be considered in the underlying contracts given the new IFR include the following:

Contract

Questions to ask

Customer agreements (GPU-as-a-service, capacity reservation, master services)

 

Who is the customer's ultimate parent? Can the customer resell capacity or train models for third parties?

Colocation and leases

 

Does the operator have visibility of its tenants' end customers?

GPU supply, server purchase and integration

 

Who applies for the licence? What happens to delivery and price if it is delayed or refused?

Change in law, force majeure and illegality

 

Does the IFR fall within these clauses? Was it foreseeable? Who bears the cost?

Expansion and capacity allocation

Could reallocation take a Restricted Company over the threshold across linked sites?

 

Confidentiality and data protection

Can the operator lawfully share customer ownership data with suppliers and BIS?

 

It is important to be aware of mismatches across the contract stack and plan a lawful continuity route. This is important as if a customer contract is suspended for regulatory reasons while take-or-pay obligations under power, lease or GPU purchase arrangements continue, the project carries a stranded cost. Sponsors, borrowers and financiers should also consider if there is a practical ability to replace customers, equipment, operators or sites, including consent and licensing implications, and preserve essential power, cooling, connectivity and software access during a transition.

3. Other financing considerations

Due diligence

In addition to the above, lenders should add IFR-specific questions to their diligence including:

  • Whether a destination-based or end-use licence is needed, whether it has been obtained, on what conditions and by whom.
  • The customer book, including revenue derived from Restricted Companies or their intermediaries, concentration by ultimate beneficiary and contracting customer, a downside case in which those contracts are suspended and any ownership changes.
  • The borrower's KYC and export control compliance programme, noting that KYC needs to reach each customer's headquarters and ultimate parent and any direct or indirect ownership or control by persons located in China, Macau or another Country Group D:5 country.

 

Collateral and enforcement

GPU collateral is worth what it can lawfully be used and sold for and a sale on enforcement is itself a transfer or reexport that may need a licence. Buyer pools may also be further narrowed given the new IFR. Lenders should reflect this in valuations, advance rates and enforcement planning. Lenders should further bear in mind the Export Administration Regulations (EAR) general prohibition on proceeding with a transaction with knowledge that a violation has occurred or is about to occur. It remains important to diligence landlord liens and equipment access and removal rights and to have direct agreements covering non-disturbance, cure and step-in rights.

Documentation

Lenders should consider including in facility documentation, among other things:

  • Evidence that required licences are held, or that none are required, as conditions precedent to utilisation.
  • Representations and undertakings on compliance with US export controls including the IFR, maintenance of an adequate KYC programme, restrictions against capacity reallocation that would trigger an unlicensed transfer and a requirement to obtain and maintain licences.
  • Information covenants including periodic reporting on licence status, compute allocation, customer ownership and concentration.
  • Licence refusal or revocation, entity list designation and loss of material customer contracts as events of default or mandatory prepayment events.

 

Practical next steps

For sponsors and borrowers

  • Map the relevant data centre facilities, customers and linked sites and calculate the aggregate TPP made available to Restricted Companies.
  • Diarise the key dates for implementation of any changes to the Export Administration Regulations (EAR).
  • Build licence timing into project schedules and GPU supply contracts.
  • Refresh customer contracts, KYC questionnaires and data sharing consents.

 

For financiers

  • Add IFR-specific questions to due diligence requirements.
  • Review existing portfolio exposure, particularly GPU-backed and contracted revenue facilities.
  • Revisit collateral valuations and enforcement plans.
  • Engage early with sponsors and borrowers on the licensing timetable and its effect on drawdowns.

The IFR is interim and may change after the comment period. We will continue to monitor developments and their effect on transactions in the region and provide further guidance in due course.  