On 11 February 2020, the Federal Electricity Commission (CFE), published in the Official Federal Gazette the international tender for contracting the service of installation, supply, commissioning and comprehensive support of EV charging vehicles.
Description of Services:
In accordance with the tender specifications, the types of service being tendered to include (i) supply; and (ii) installation.
Principal details of the tender:
Interested entities, who may participate jointly, will not need to form a company. The common representative who has been previously designated must sign the joint bid electronically.
The contracting process of the project will be carried out using the CFE's tendering electronic site, thus this procedure has the particularity of being carried out electronically.
Relevant dates:
The most relevant dates of the bid are the following:
# | Action / Activity | Date |
1 | Publish of the document with the list of requirements | February 5, 2020 |
2 | Period of submitting request for classifications of the document with the list of requirements |
From: February 5, 2020, |
3 | Clarifications of the contest documents | February 11, 2020 |
4 | Limit for the submission of offers of the contestants and required information | February 20, 2020 |
6 | Submission and opening of the technical proposals | February 20, 2020 |
7 | Opening of the economic proposals | February 27, 2020 |
8 | Announcement of the winning bidder | March 4, 2020 |
9 | Execution of the contract | The date and time will be indicated in the corresponding record contest result |
10 | Beginning of the construction of the Plant | 15 days after the award |
Our Firm will be glad to answer any inquiry or provide any service regarding this matter.